Procurement is sourcing and buying what a business needs; lead time is the gap between placing an order and receiving it. Free notes and 14 questions answered.

Updated 5 Mar 2026 · Revise Right Team

Procurement: JIT, JIC, Price & Quality is part of The role of procurement in GCSE AQA Business.

7 min

Reading time

11

Lessons in this topic

GCSE AQA

Pathway

Reviewed by Revise Right

Content review

What this lesson covers

Procurement is sourcing and buying what a business needs; lead time is the gap between placing an order and receiving it. Free notes and 14 questions answered.

  • Define Just in Time (JIT) and Just in Case (JIC) stock management approaches
  • Explain the factors a business considers when choosing suppliers, including price, quality, and reliability
  • Compare the advantages and disadvantages of JIT and JIC for different business contexts
  • Calculate stock-related costs and interpret stock control charts to inform procurement decisions

Key ideas to keep in view

Use this lesson to stay inside The role of procurement while connecting the detail back to the wider Business operations topic.

  • Business operations
  • The role of procurement
  • GCSE AQA Business

Revision notes

Read the core explanations from Procurement: JIT, JIC, Price & Quality before testing yourself from memory.

1. Why Procurement Decisions Make or Break a Business

A car manufacturer runs out of a single bolt. The entire production line stops. Thousands of workers stand idle, and the business loses hundreds of thousands of pounds per hour. This is not a hypothetical — it happened to several manufacturers during global supply chain disruptions in 2021.

Procurement is the process of sourcing and buying everything a business needs to operate — from raw materials to packaging. Get it right, and costs stay low, production runs smoothly, and customers receive their orders on time. Get it wrong, and the consequences ripple through every part of the business.

At the heart of procurement sits one fundamental question: how much stock should a business hold at any given time? The answer depends on the approach the business takes — and the two main approaches are Just in Time and Just in Case.

2. Stock Management: JIT and JIC

Think of stock management like a kitchen. One chef keeps the fridge packed with every ingredient imaginable — they never run out, but food spoils and the fridge costs a fortune to run. Another chef orders ingredients fresh each morning, using exactly what is needed — no waste, but if the delivery is late, there is nothing to cook. These two approaches map directly onto JIC and JIT. The choice between JIT and JIC depends on various factors, such as the type of products being managed, customer demand patterns, and the nature of supplier relationships.

The choice between JIT and JIC is not about preference — it reflects the nature of the business, its industry, and its relationship with suppliers. A business selling fresh food cannot hold weeks of stock. A business manufacturing aircraft parts cannot afford to halt production because a single component failed to arrive.

FeatureJust in Time (JIT)Just in Case (JIC)
Stock heldMinimal — ordered as neededLarge buffer maintained
Storage costsLowHigh
Risk of stockoutHigh if supplier failsLow — buffer absorbs disruption
Cash tied up in stockLow — frees working capitalHigh — capital locked in stock
Waste riskLow — stock is fresh/currentHigher — stock may expire or become obsolete
Supplier reliability neededCritical — must be very highLess critical — buffer provides cover
Best suited toPredictable demand, fast suppliersUnpredictable demand, long lead times

Notice the trade-off at the core of this table. JIT frees up cash and cuts waste, but it transfers risk onto the supply chain. JIC absorbs that risk by holding stock, but ties up working capital and increases costs. Neither approach is universally superior — the right choice depends on context.

3. Choosing Suppliers: Price, Quality, and Reliability

Deciding between JIT and JIC is only half the procurement decision. The other half is choosing which supplier to buy from. A business might identify three potential suppliers for the same component — but they differ on price, quality, and how reliably they deliver on time. These three factors sit at the centre of every procurement decision.

Price is the most visible factor in procurement — a lower purchase price directly reduces the cost of production, improving gross profit margin. However, choosing the cheapest supplier without considering quality or reliability can be a costly mistake. A component that fails during production causes delays, waste, and potential damage to the finished product.

Quality refers to whether the materials or components meet the required standard consistently. For a business like a car manufacturer, a substandard component does not just waste money — it creates safety risks and potential product recalls. The cost of poor quality almost always exceeds the saving made by choosing a cheaper supplier.

These three factors — price, quality, and reliability — rarely all point to the same supplier. A business must weigh them against each other based on its priorities. A hospital prioritises quality and reliability above price. A budget retailer may prioritise price, accepting slightly lower quality. This is where procurement becomes a genuine strategic decision.

4. Reading and Interpreting Stock Control Charts

Procurement decisions do not happen in isolation — they are guided by stock control data. A stock control chart gives a business a visual picture of how stock levels change over time, when to reorder, and how much to order. Understanding how to read one is an essential exam skill.

Three horizontal reference lines appear on a stock control chart. The maximum stock level is the upper limit — holding more than this is wasteful and costly. The reorder level is the trigger point: when stock falls to this level, a new order is placed. The minimum stock level (buffer stock) is the safety net — stock should never fall below this line under normal circumstances.

The sawtooth pattern on the chart is characteristic of stock management. Stock falls steadily as it is used in production, then jumps back up when a delivery arrives. The gap between placing an order and receiving it is the lead time — and this is why the reorder level must be set high enough to cover usage during that lead time.

Look at Week 9 on the chart above. Stock has fallen to 100 units — the minimum stock level. This signals a problem: either the reorder was placed too late, or the supplier's lead time was longer than expected. A JIT business in this position would face a production stoppage. A JIC business with a larger buffer would have more breathing room.

Worked example: Calculating Reorder Level from Lead Time and Usage Rate

A manufacturer uses 100 units of Component Y per week. The supplier's lead time is 3 weeks. The business wants a buffer stock of 150 units. Calculate the reorder level.

  1. Reorder Level = (Usage per week x Lead time in weeks) + Buffer stock — The reorder level must cover all stock used during the lead time, plus keep the buffer intact. This ensures stock never falls below the minimum level while waiting for delivery.
  2. Usage during lead time = 100 units per week x 3 weeks = 300 units — During the 3-week wait for delivery, the business will use 100 x 3 = 300 units. This is the minimum stock needed just to survive the lead time.
  3. Reorder Level = 300 + 150 = 450 units — The buffer stock of 150 units is added on top. This means even if demand spikes or the supplier is slightly late, the business will not run out of stock.
  4. When stock falls to 450 units, place a new order immediately. — Setting the reorder point at 450 units gives the business 3 weeks of production cover plus a 150-unit safety buffer. A JIT business would set a much lower buffer — or none at all — accepting higher risk in exchange for lower storage costs.

Answer: Reorder Level = 450 units. The business should place a new order when stock reaches 450 units.

5. Applying Procurement Decisions: A Worked Scenario

Theory becomes meaningful when applied to a real decision. Consider Priya, who runs a small furniture manufacturer called CraftWood Ltd. She currently uses JIC, holding 8 weeks of timber stock at all times. Her accountant has pointed out that the storage costs alone are costing the business £24,000 per year. A local timber merchant has offered to supply timber within 48 hours of any order, at a price 5% higher per unit than her current supplier.

Priya is weighing up whether to switch to JIT using the local merchant. This is exactly the kind of procurement decision that appears in AQA exam questions — and it requires you to weigh up multiple factors, not just pick the cheapest option.

Worked example: Evaluating a Procurement Decision: JIT vs JIC for CraftWood Ltd

CraftWood Ltd currently spends £480,000 per year on timber under JIC. Storage costs are £24,000 per year. A local JIT supplier charges 5% more per unit but eliminates storage costs. Evaluate whether switching to JIT is financially beneficial.

  1. Current timber cost: £480,000. Storage cost: £24,000. Total JIC cost = £480,000 + £24,000 = £504,000 — Under JIC, the business pays for both the stock itself and the cost of storing it. Both must be included to get the true cost of the current approach.
  2. Price increase = 5% of £480,000 = 0.05 x £480,000 = £24,000. New timber cost = £480,000 + £24,000 = £504,000 — The JIT supplier charges 5% more per unit. 5% of £480,000 = £24,000, so the new annual timber spend rises to £504,000.
  3. JIT timber cost: £504,000. Storage cost: £0 (no stock held). Total JIT cost = £504,000 — Under JIT, the business holds no stock, so storage costs are eliminated entirely. The total cost is the new timber spend.
  4. JIC total: £504,000. JIT total: £504,000. Difference = £0 — In this scenario, the financial saving from eliminating storage costs exactly offsets the higher unit price. The decision cannot be made on cost alone — other factors must be considered.
  5. JIT benefits: frees working capital, reduces waste risk, fresher materials. JIT risks: production halts if the local supplier fails to deliver within 48 hours; no buffer if demand spikes unexpectedly. — When the financial case is neutral, non-financial factors become decisive. Priya should assess how reliable the local supplier is and whether CraftWood's demand is predictable enough to make JIT viable.

Answer: Switching to JIT is financially neutral in this case — the higher unit price is offset by eliminated storage costs. The decision should be based on supplier reliability and demand predictability. If the local merchant has a strong track record and CraftWood's orders are consistent, JIT is the better long-term choice as it frees working capital and reduces waste.

6. Exam Technique: Procurement Questions

Procurement questions on AQA GCSE papers tend to follow predictable patterns. You will be given a business scenario and asked to explain, analyse, or evaluate a procurement decision. The marks are in the development — not the identification. Saying 'JIT reduces storage costs' earns one mark. Explaining why this matters for the specific business in the question earns two or three.

For evaluate questions (typically 9 or 12 marks), you must argue both sides. A strong answer on JIT vs JIC will acknowledge that JIT reduces costs and waste, then counter with the risk of production stoppages if suppliers fail. The conclusion must make a justified judgement — not sit on the fence. Use phrases like 'On balance...' or 'Given that the business operates in...' to signal your evaluative judgement.

When a question asks you to 'use the data', you must quote specific figures from the source material. Saying 'the business has high storage costs' is generic. Saying 'the business spends £24,000 per year on storage, which represents approximately 4.8% of its total procurement cost' is applied — and that is where the higher marks sit.

Frequently asked questions

What is lead time?

Lead time is the gap between placing an order with a supplier and receiving it. The reorder level must be set high enough to cover the stock used during the lead time, so a longer lead time needs a higher reorder level.

What is procurement?

Procurement is the process of sourcing and buying everything a business needs to operate, from raw materials to packaging. Good procurement keeps costs low and production smooth, while poor procurement can stop a production line, as when manufacturers ran short of parts during supply chain disruptions in 2021.

How do you read a stock control chart?

A stock control chart shows stock falling steadily as it is used, then jumping up when a delivery arrives, in a sawtooth pattern. It has three reference lines: the maximum stock level, the reorder level that triggers a new order, and the minimum (buffer) stock level, which stock should not normally fall to.

What is buffer stock?

Buffer stock is the minimum stock level, a safety net that stock should never fall under in normal circumstances. It protects against demand spikes or late deliveries, and it is added to usage during the lead time to set the reorder level.

How do you calculate the reorder level?

Reorder level = (usage per week × lead time in weeks) + buffer stock. A manufacturer using 100 units a week, with a 3-week lead time and a buffer stock of 150 units, has a reorder level of (100 × 3) + 150 = 450 units, so it places a new order when stock falls to 450.

What is the difference between Just in Time and Just in Case?

Just in Time (JIT) means ordering materials only when they are needed, holding minimal stock, which cuts storage costs and waste but risks a stockout if a supplier fails. Just in Case (JIC) means deliberately holding large buffer stocks against demand surges or supply disruption, which is safer but ties up cash and raises storage costs.

What is the maximum stock level?

The maximum stock level is the upper limit on a stock control chart: holding more stock than this is wasteful and costly. It is one of three reference lines, alongside the reorder level, which triggers a new order, and the minimum stock level, or buffer stock.

Why do price, quality and reliability matter when choosing a supplier?

Price, quality and reliability sit at the centre of every procurement decision. A lower price cuts production costs, but poor-quality components cause delays, waste and even product recalls, and a supplier with low reliability can halt production, especially for a JIT business, so the cheapest supplier is not always the best.

What is Just in Case stock management?

Just in Case (JIC) stock management is deliberately holding large quantities of stock as a safety buffer against unexpected demand surges or supply chain disruptions. Examples are a supermarket holding extra tinned goods before a predicted storm or a hospital keeping large reserves of medicines.

When is Just in Case better than Just in Time?

Just in Case is better than Just in Time when demand is unpredictable, supplier lead times are long, or a stockout would be very costly, such as for a hospital or an aircraft parts manufacturer. The buffer absorbs disruption, though it ties up working capital and raises storage costs.

Is the cheapest supplier always the best?

The cheapest supplier is not always the best, because a low price can come with poor quality or late deliveries. A component that fails causes delays, waste and potential product recalls, so the cost of poor quality usually exceeds the saving; a hospital, for example, puts quality and reliability before price.

What is supplier reliability?

Supplier reliability is how consistently a supplier delivers the correct goods, in the correct quantity, at the correct time. A supplier with a 98% on-time delivery record is highly reliable; high reliability is essential for JIT businesses, where a late delivery can halt production.

Why does a stock control chart have a sawtooth shape?

A stock control chart has a sawtooth shape because stock falls steadily as it is used in production, then jumps back up when a delivery arrives. The gap between placing an order and receiving it is the lead time, which is why the reorder level must cover usage during that time.

How do you compare the costs of JIT and JIC?

The costs of JIT and JIC are compared by adding stock and storage costs for each. CraftWood Ltd pays £480,000 for timber plus £24,000 storage under JIC, £504,000 in total; a JIT supplier charging 5% more also costs £504,000 with no storage, so the choice rests on supplier reliability and predictable demand.